Year 0: June 2023-May 2024
-
2023
-
Jun
-
Award announced
-
-
Jun
-
2024
-
May
-
B&P Approval
-
-
May
Year 1: June 2024-May 2025
-
2024
-
Nov
-
CFI Finalized
-
-
Nov
-
2025
-
Jan
-
CFI Report #1
-
-
Feb
-
Facility RFSQ
-
-
Mar
-
RFPs
-
-
Jan
Year 2: June 2025-May 2026
-
2025
-
Jun
-
Begin construction
-
-
Jun
Year 3: June 2026-May 2027
-
2026
-
Sep
-
Partical occupancy
-
-
Dec
-
Linac/Modulators
-
-
Sep
-
2027
-
Jan
-
Install begins
-
-
Nov
-
End construction
-
-
Jan
Year 4: June 2027-May 2028
-
2027
-
Jun
-
Undulators installed
-
-
Aug
-
Commissioning begins
-
-
Sep
-
Install End-stations (begins)
-
-
Dec
-
Install End-stations (ends)
-
-
Jun
-
2028
-
Jan
-
First Light
-
-
Feb
-
Commission End-stations (begins)
-
-
May
-
Commission End-stations (ends)
-
-
Jan
Year 5: June 2028-May 2029
-
2028
-
Jun
-
SOPs, proof-of-concept (begins)
-
-
Sep
-
SOPs, proof-of-concept (ends)
-
-
Oct
-
First users
-
-
Jun
Year 6: June 2029-May 2030
-
2029
-
Dec
-
CFI end
-
-
Dec
-
2030
-
Jan
-
Final report
-
-
Jan